Enemalta lays 6km of cables to strengthen Birkirkara’s electricity network

The project by Enemalta to lay 6km of cables in Birkirkara will replace sections of cable prone to faults and add around 600 metres of new low-voltage lines to strengthen electricity network

The Birkirkara works include replacing sections of existing 11kV cable and laying additional 11kV lines. Both will strengthen the medium-voltage network serving several parts of the town
The Birkirkara works include replacing sections of existing 11kV cable and laying additional 11kV lines. Both will strengthen the medium-voltage network serving several parts of the town

Enemalta has laid around 6km of cables across Birkirkara to strengthen the town’s electricity network

“We are not simply responding to today’s electricity demand, but anticipating tomorrow’s needs,” Dalli said during a visit to the site with Enemalta and representatives of the Birkirkara local council on Thursday.

The works form part of Enemalta’s nine-year plan to reinforce, renew and expand the electricity distribution network across both islands. The plan covers investment in cables, feeders, substations, distribution centres and other electricity infrastructure.

The Birkirkara works include replacing sections of existing 11kV cable and laying additional 11kV lines. Both will strengthen the medium-voltage network serving several parts of the town.

“The Birkirkara project combines the installation of new 11kV infrastructure with the renewal of sections of the existing network that are more vulnerable to faults due to the number of cable joints,” engineer Etienne Lewis said.

Enemalta is also adding around 600 metres of low-voltage lines to reinforce that part of the network, and the upgrades would increase capacity and make the network more reliable.